The AMDAL (Analisis Mengenai Dampak Lingkungan) is Indonesia’s environmental impact assessment framework. For any tourism accommodation development above the threshold size, AMDAL approval is a legal prerequisite for obtaining a building permit (PBG). It cannot be bypassed or expedited through unofficial channels it is a formal government process with statutory timelines.
For tourism accommodation projects, the AMDAL threshold is triggered when any of the following apply:
All three development scenarios modelled for the Sidemen Serenity Estate trigger the AMDAL threshold. Stages 1 and 2 together significantly exceed 5,000 m² of built floor area.
| Stage | Description | Typical Duration | Lead Party |
|---|---|---|---|
| KA-ANDAL (Terms of Reference) | Scoping document identifying key environmental issues to be studied | 2 to 3 months | Licensed AMDAL consultant (LPJP) |
| Environmental baseline studies | Field studies: flora, fauna, hydrology, traffic, socioeconomics | 3 to 6 months concurrent | AMDAL consultant field team |
| ANDAL document preparation | Full environmental impact assessment document prepared and submitted | 2 to 3 months | AMDAL consultant |
| Government review and public consultation | Komisi AMDAL review; public meetings with affected communities | 2 to 4 months | Karangasem Dinas Lingkungan Hidup |
| SKKL (Environmental Feasibility Decision) | Formal approval prerequisite for PBG building permit lodgement | 1 to 2 months | Karangasem / Provincial authority |
| Total AMDAL timeline estimate | 10 to 18 months |
| Cost Item | Estimated Range (AUD) | Notes |
|---|---|---|
| AMDAL consultant (LPJP-accredited) | 80,000 to 180,000 | Depends on study complexity and community consultation scope |
| Government fees and administration | 5,000 to 15,000 | BPN, DPMPTSP, Dinas LH administrative costs |
| Community consultation costs | 10,000 to 25,000 | Meetings, documentation, translation, travel |
| Total AMDAL budget estimate | 95,000 to 220,000 | Included in development cost model |
The AMDAL process must start before any other construction-related permitting and runs concurrently with HGB title conversion. Understanding this sequencing is essential for development programme planning.